If you have any gueries, get in touch today! Don't hesitate, We try to take the extra step for our customer satisfaction.
Date:22/08/2024
The planned total capacity of the project is 300 MW/600 MWh (that is, the maximum charging and discharging power reaches 300 MW, and the total storage capacity reaches 600 MWh). power generation.
The project is divided into three phases. In the first phase, a 100MW/200MWh energy storage system and a 220kV booster station will be built. The world's advanced 1500V liquid-cooled lithium iron phosphate energy storage technology will be used. Store 200,000 kWh of clean electricity, effectively improving the comprehensive utilization of new energy resources and the safe and stable operation of the power grid. On December 30, 2021, the first phase of the project has been successfully connected to the grid, which has comprehensively improved the Qingyun county power grid's "peak-shifting and valley-filling" adjustment capabilities, and helped Qingyun realize "24-hour green power supply".